Archive for August, 2013

A Hospital Pharmacy Renovation – Milestone On Times, Issue #7, October 2010

August 19th, 2013

Here at Milestone, we have so much good information that is sent out over a variety of media, that we thought it would be a good idea if we brought up some past articles from our quarterly newsletter, Milestone On Times.  This article on one of our Pharmacy Renovations, was in the October 2010 issue of MoT.

We hope you enjoy it:

St. Luke’s Hospitals Complete Two USP 797-Compliant Pharmacy Renovations

SLEH Pharmacy
Photography by Geoff Lyon

St. Luke’s Episcopal Hospital and St. Luke’s The Woodlands Hospital recently completed renovations to bring their pharmacies into compliance with USP 797 guidelines.

At St. Luke’s Episcopal Hospital, it was determined by the Pharmacy Department that a new negative pressure chemotherapy prep room was needed in order to comply with USP 797. Because the existing clean room and pharmacy work rooms were required to remain operational during the entirety of the construction, much time was spent planning the construction and occupation sequence.  Careful coordination of the equipment relocation ensured that the pharmacy suffered no downtime; the staff always had ability to prepare IVs and chemotherapy products.

At St. Luke’s The Woodlands, the renovation included the expansion of the existing pharmacy and lab by nearly 1,300 SF. To meet the requirements of USP 797, a new chemotherapy prep room, IV prep room and an anteroom were added.  In order to maintain pharmacy operations, the project was design to be completed in three separate phases, which would require a minimum of three separate TDSHS inspections. To renovate the existing clean room, a temporary clean room was setup outside of the project area so that operations could continue. And with a little creativity, the project team was able to sequence the construction (rather than complete the work in phases) so that only an 80% and 100% inspection were required.

Milestone Project Management was engaged by St. Luke’s Episcopal Health System to manage the design and construction process for both projects.

PhiloWilke Partnership (Architecture) and Telios (MEP) comprised the design team for the St. Luke’s Episcopal Hospital renovation.  WS Bellows’ Medical Center Renovation Team served as the Construction Manager.

For the Woodlands’ hospital, HGA provided both architecture and MEP engineering services. Forney Construction was the Construction Manager.